Cost and Schedule Policy

This is a program-framing ROM. It is not a supplier quote, an independently validated cost estimate, or an approved funding or schedule baseline.

Cost range

Case WBS base (M AUD) Reserve Reserve (M AUD) Total (M AUD)
low 544.00 15.0% 81.60 625.60
planning 809.00 25.0% 202.25 1011.25
high 1218.00 40.0% 487.20 1705.20

Cost work breakdown

ID Work package Released subsystems Basis type Low / planning / high (M AUD) Owner
CST-01 Program management, systems engineering, safety, mission assurance, and product assurance cross-cutting engineering_judgement 45.0 / 65.0 / 95.0 program manager
CST-02 Optical payload and detector development optics, detector engineering_judgement 90.0 / 140.0 / 220.0 payload lead
CST-03 Structures and deployment mechanisms structures_and_mechanisms engineering_judgement 35.0 / 55.0 / 90.0 mechanical lead
CST-04 Thermal-control subsystem thermal_control engineering_judgement 20.0 / 32.0 / 50.0 thermal lead
CST-05 Electrical power subsystem power engineering_judgement 18.0 / 28.0 / 45.0 electrical power lead
CST-06 Propulsion subsystem propulsion engineering_judgement 15.0 / 25.0 / 40.0 propulsion lead
CST-07 Attitude determination and control subsystem adcs engineering_judgement 20.0 / 32.0 / 50.0 GNC lead
CST-08 Command and data handling subsystem cdh engineering_judgement 15.0 / 24.0 / 38.0 avionics lead
CST-09 RF communications subsystem communications engineering_judgement 18.0 / 28.0 / 45.0 RF lead
CST-10 Flight software and FDIR flight_software engineering_judgement 25.0 / 40.0 / 65.0 flight software lead
CST-11 Assembly, integration, verification, GSE, and facilities cross-cutting planning_allowance 45.0 / 70.0 / 110.0 AIV manager
CST-12 Ground segment and mission-operations preparation cross-cutting planning_allowance 18.0 / 30.0 / 50.0 mission operations manager
CST-13 Launch service, mission-specific launch integration, and insurance allowance cross-cutting planning_allowance 180.0 / 240.0 / 320.0 launch services manager

Schedule

Phase Months Critical path Predecessors Owner Exit evidence
SCH-01 Requirements maturation and system definition 0-9 yes none chief systems engineer System requirements review closes the mission, interface, verification, cost, and schedule baselines for preliminary design.
SCH-02 Preliminary design and technology-risk retirement 9-21 yes SCH-01 chief engineer Preliminary design review closes subsystem allocations, credible interfaces, breadboard evidence, and long-lead release authority.
SCH-03 Detailed design and engineering-model release 21-39 yes SCH-02 chief engineer Critical design review releases controlled drawings, software architecture, procurement data, and engineering-model configurations.
SCH-04 Engineering and qualification articles 39-54 yes SCH-03 qualification manager Qualification readiness review confirms representative articles, facilities, GSE, procedures, and non-conformity control are ready.
SCH-05 Flight manufacture and observatory integration 54-66 yes SCH-04 AIV manager Integrated flight observatory completes functional, alignment, workmanship, and configuration audits before acceptance testing.
SCH-06 Environmental acceptance and launch readiness 66-72 yes SCH-05 mission assurance manager Acceptance campaign, end-to-end mission rehearsal, shipment review, and launch readiness review close without open flight-critical waivers.
SCH-07 Launch campaign and commissioning 81-84 no SCH-06 mission director Launch, early operations, deployment, calibration, and commissioning acceptance establish the released nominal-science configuration.

Milestones

ID Milestone Month Phase
MS-SRR System requirements review complete 9 SCH-01
MS-PDR Preliminary design review complete 21 SCH-02
MS-CDR Critical design review complete 39 SCH-03
MS-QRR Qualification readiness review complete 54 SCH-04
MS-FIR Flight integration complete 66 SCH-05
MS-LRR Launch readiness review complete 72 SCH-06
MS-LAUNCH Commitment launch milestone 81 SCH-07
MS-COMMISSION Commissioning acceptance complete 84 SCH-07

Dominant cost and schedule risks

ID Risk Cost WBS Schedule phases Owner Treatment
RSK-01 Primary-mirror fabrication yield or detector procurement extends the payload critical path and forces replacement hardware. CST-02 SCH-02, SCH-03, SCH-04 payload lead Retire mirror-process and detector-supply risks before PDR, preserve qualification spares, and gate flight procurement on representative evidence.
RSK-02 Deployment mechanism life testing exposes release, synchronization, routing, or retained-capture redesign. CST-03, CST-11 SCH-03, SCH-04 mechanical lead Build representative mechanism articles early, test across thermal extremes, and preserve schedule for redesign before flight manufacture.
RSK-03 Fine-pointing and wheel-induced jitter exceed the optical line-of-sight allocation during integrated testing. CST-07, CST-11 SCH-02, SCH-03, SCH-04 GNC lead Add disturbance testing and integrated structural-optical correlation before CDR and retain isolation design authority.
RSK-04 Environmental or end-to-end acceptance failures require observatory disassembly and repeat testing. CST-01, CST-11 SCH-05, SCH-06 mission assurance manager Use qualification articles, incremental workmanship tests, controlled non-conformity closure, and explicit test-repeat allowances.
RSK-05 Ground-station access, licensing, or interface work differs from the representative two-site CONOPS. CST-09, CST-12 SCH-02, SCH-03, SCH-05 mission operations manager Secure network agreements and regulatory strategy before PDR and validate RF and mission-control interfaces with representative ground equipment.
RSK-06 Launch-service contracting, rideshare allocation, or mission-specific integration differs from the internal Ariane 6 allowance. CST-13 SCH-02, SCH-05, SCH-06 launch services manager Obtain provider budgetary data during formulation, preserve interface-change control, and carry cost and schedule reserves until contract signature.
RSK-07 Radiation-tolerant avionics lead times or obsolescence force C&DH, power, RF, or software rework. CST-05, CST-08, CST-09, CST-10 SCH-02, SCH-03, SCH-05 avionics lead Freeze the approved-parts strategy early, procure engineering lots before CDR, and maintain compatible alternates.
RSK-08 Specialised cleanroom, thermal-vacuum, vibration, acoustic, shock, or optical-alignment facilities are unavailable at the planned dates. CST-11 SCH-03, SCH-04, SCH-06 AIV manager Place provisional facility reservations during preliminary design and qualify alternate facilities and transport plans before CDR.

Explicit exclusions

Checks

Check Result
cost_schedule_policy_schema_supported PASS
cost_schedule_basis_matches_released_program PASS
cost_schedule_upstream_release_evidence_passes PASS
cost_wbs_ranges_and_reserves_are_complete PASS
cost_wbs_covers_every_released_subsystem_once PASS
schedule_logic_reserve_and_subsystem_coverage_close PASS
schedule_milestones_match_phase_and_commitment_boundaries PASS
cost_schedule_risk_drivers_are_owned_and_traceable PASS